Juniper Green Energy has fully commissioned its 150 MW wind-solar hybrid power project in Gujarat, secured under a Power Purchase Agreement (PPA) with Gujarat Urja Vikas Nigam Limited (GUVNL).
The project reached full operational status on October 12, 2026, with the successful commissioning of its final 5 MW wind turbine, verified on-site by officials from the Gujarat Energy Development Agency (GEDA) and Paschim Gujarat Vij Company Limited (PGVCL). Formal certification is expected shortly. With this milestone, Juniper Green Energy and its subsidiaries now command an operational capacity of approximately 2,745 MWp alongside 603 MWh of Battery Energy Storage Systems (BESS).
Additionally, on October 1, 2026, the company’s wholly-owned subsidiary, Juniper Green Stellar Energy Private Limited, commissioned 15.5 MW of wind capacity as part of a larger 200 MW Firm and Dispatchable Renewable Energy (FDRE) project.
News by Rahul Yelligetti.